London Road Progress Update: 11th March 2025

London Road is rapidly taking shape, and for the first time, the building is truly beginning to feel like a home. With the structure in place and finishing touches underway, we’re making great progress towards completion.


 

Final Fixes & Interior Advancements


On the top floor, all areas have now been mist-coated, with doors installed and floors fully tiled. The final layer of ply is down, ensuring a perfect base for the final flooring installation. The plasterer will be back this weekend to complete the last tricky section—once that’s done, we’ll be fully ready for the next stage of decorating.


Moving down to the first floor, the painting is almost complete, and our team is working on fitting doors. Skirting boards and architraves have arrived and are being installed, adding those essential finishing details. Dehumidifiers are running across the site, ensuring moisture levels are optimal before further work continues.



 

Bathroom & Flooring Installations Underway


  • Bathroom tiling is progressing well, with shower panels starting to go up. The feature panels have been slightly delayed but should arrive by the end of next week.

  • Corridor views are shaping up as more doors are hung and finishes are applied.

  • Throughout the building, floors are being tiled, with multiple rooms already completed.


 

Ground Floor & External Progress Updates


  • The water main is now in place, and ready for connection.

  • The bin store has been a key focus this week—it's now fully slabbed, drained, and prepped for cladding with hygiene board for easy maintenance.

  • Insulation has been fitted throughout the ground floor, with tackers completing their work in multiple rooms. Most walls are now boarded, with only the brickwork left to be drylined next week.


Meanwhile, the kitchen is fully boarded and ready for plastering, bringing us another step closer to completion.


 

External Works: Nearly There


Outside, the communal area cladding is finished, and we’re awaiting the arrival of the polycarbonate roof. The bike store is already functional, providing much-needed storage space.


The top half of the building is now fully painted, and the final coat on the lower section will be completed tomorrow. Once the downpipes are installed, we’ll have a fully weatherproof, dry building—essential for protecting the high-quality finish inside.


 

What’s Next?


✅ Complete painting & exterior finishing touches

✅ Install remaining shower panels and doors

✅ Finalise tiling & flooring

✅ Connect water main and board in remaining areas

✅ Begin the final decorating phase


With everything moving at this pace, we’re on track for the final stages of completion. Stay tuned for the next update as we bring this project to life!





 

DISCLAIMER


Aura Property Ventures Ltd works with High Net Worth or Sophisticated Investors only. Any information provided here is not for public promotion and is not to be regarded as an FCA-approved regulated investment.


Please read our terms and conditions relating to the use of this site for further information.


bottom of page